泥水工安全技術交底
一、砌體施工:
⒈挖掘土方,兩人操作間距保持2~3m,并由上而下逐層挖掘,禁止采取掏洞的操作方法。
⒉開挖溝槽、基坑等,應根據土質和現場施工員交底放坡,挖出的泥土應堆放在坑槽邊1m以外,堆高不得超過1.5m。
⒊砌基礎時,應檢查和經常注意基坑土質變化情況,有無崩裂現象。堆放材料應離開坑槽邊1m以上。當基坑較須設護壁支撐時,操作人員應設梯子上下,不得攀跳,運料不得碰撞支撐。
⒋墻身砌體高度超過1.2m時,應搭設腳手架。在一層以上或高度超過4m時采用里腳手架必須在墻外張掛安全網,采用外腳手架應綁護身欄桿后方準操作。
⒌用內架砌外墻時,架板要低于外墻20cm,墻外按規定張掛安全網。
⒍腳手架上堆磚不得超過三皮,架子轉角處不得堆砧,除操作層外,上下皮架只允許堆零星材料,不得多層都堆料。
⒎在高處砌墻時,轉砧應面向墻面,工作完畢應將腳手板和磚墻上的碎磚,灰漿清掃干凈,防止掉落傷
Plasterers Security Technology Details
1, Masonry Construction:
⒈ excavation of earth to keep distance between the two operations 2 ~ 3m, and top-down floor by floor mining, prohibit the operation method to dig holes.
⒉ trench excavation, foundation, etc., should be based on soil and site construction workers clarification at Slope, excavated soil should be stacked outside the pit side of 1m, forklifts must not exceed 1.5m.
⒊ puzzle base, the foundation should be checked and regular attention to soil changes, with or without crack phenomenon. Stacking materials, leave the pit side for more than 1m. When the pit wall protection shall be provided more support, the operator should set the ladder up and down, not climbing jump, transport material may not impact support.
⒋ masonry wall height of more than 1.2m should scaffold erection. In the layer above or more than 4m high scaffold to be used in wall hung safety nets, scaffolding should be tied to protect oneself by external standards operate behind bars.
⒌ with the external walls and inside the frame, the frame is lower than the wall plate 20cm, wall display in accordance with the provisions of the safety net.
⒍ scaffold shall not exceed three skin brick heap, not stack anvil corner shelf, in addition to operating level, the upper and lower frame allows only heap sporadic skin material, not multi-piled material.
⒎ the high walls, the switch should be oriented anvil wall, should be completed working on the scaffold board and brick walls broken brick, mortar cleaned to prevent falling injuries